In order for the building to be integrated into the flower square, it was necessary to remove the 4 pillars supporting the leisure area floor from the project, thus leaving a large gap of almost 25m in length. Shoring of transition beams of 3.5 wide by 2 .5m high. Load of 22tf/m;
Concreting the beams in a single step.
C4 concrete, liquid, 140 slump, temperature 18° (use of ice flakes).
A specific feature was developed with the Federal University of Ceará to meet the performance characteristics of the work. 12m ceiling height;
Support on ribbed slabs (load capacity of 150kg/m2). They could not support the weight of the transition beams; Re-shoring of 3 slabs from the basement to the support on the natural soil;
First residential development in Fortaleza – CE with
Deadline: The first study was carried out in
March 2021. Estimated deadline for the construction work
6 months from delivery of
equipment.Adherent prestressing.